35a-20220907-meath-co-co-rural-cycleway-rapid-deployment
This document is part of the request ”Meath Pathfinder Rural Cycleway Rapid Development”.
Pathfinder Project/Initiative Template Project/Initiative Title Title: Rural Cycleway Rapid Deployment Owner/Sponsor Name(s) Nicholas Whyatt Theme ☒ Active Travel ☐ Public Transport ☐ Public Realm Improvement ☐ Technology ☐ Integration ☐ Public Sector Leadership ☐ Community- Based Transport Abatement Potential ☒ High ☐ Medium ☐ Low Please briefly outline why this project/initiative carries this level of abatement potential (max c. 50 words) The project is centred on looking at methods for rapid deployment of a rural cycleway on the verges of regional roads in the county. If successful, the project could be a demonstrator project utilizing methods which could be scaled up for use on other regional roads in the county and adopted nationally. Project/Initiative Description Please give a brief description of this project (max c. 350 words) Please give a brief description of this project (max c. 350 words) Meath County Council propose to take a stretch of the R161 between Navan and Trim and adapt/hybridize current standards and some of the urban rapid deployment work that was carried out during Covid to a rural context. The aim would be to start with a trial section which would see the construction of a segregated two-way cycleway within the existing road boundary. The trial would look at pragmatic ways and cost-effective ways to construct a safe, segregated facility quickly whilst dealing with solutions to deal with segregation, drainage, boundary treatments, junction/access layouts, signage, surfacing and safety. The trial section would then be constructed and with construction supervision and engineering input any technical issues would be ‘ironed-out’ with the contractor. If successful, the trail will be scaled up to longer stretches of regional road. This project could be particularly relevant to Meath as long stretches of Strategic Regional Roads were constructed in the early 2000s on the R150 (8km), R158(16km) and R161 (10km) which have cross sections which lend themselves to being adapted to retrofit cycling and walking. In addition, significant stretches of former national roads in the county such as the R147,R135,R148 and R132 could also be adapted using methods developed during the project. The Council will comply with its statutory procurement, appraisal, planning and environmental obligations but intend to utilize to the full extent section 38 of the Roads Act 1994 (as amended) to provide traffic calming measures which facilitate the safe use of public roads by different classes of traffic (including pedestrians and cyclists), The intention would be to devise a scheme which was ‘process light’ i.e. to legitimately avoid the Part 8 process, avoid environmentally sensitive areas, avoid land take, minimize excavation, minimize utility diversions and minimize
interfering with existing drainage regimes. The hope is that by keeping costs down the appraisal requirements of the public spending code would be less onerous. The scheme will be subject to safety audits and ongoing monitoring. Note that there is no funding for this project. Impacts/Outcomes Identify the main impacts/outcomes which this project will yield by end 2025 (these may be broader in scope than what would ordinarily be thought of as ‘deliverables’ but should nevertheless be as specific and concrete as possible. For example, if a project will yield improved permeability or increased wellbeing, some thought should be given to the expected scale of change, and how it will be effectively measured. 1 Better use of existing road space 2 Provide enhanced cycling facilities quickly and efficiently. 3 Develop and adapt existing standards and processes. 4 Assist with achieving modal and climate change targets. 5 Assist with achieving Government timescales to deliver the regional and cycle networks. 6 7 Schedule Please identify any key milestones, the dates by which they must be delivered, and any potential delaying factors Date Milestone Delay Factors Q1 2023 Surveys Procurement. Staff availability and competing priorities Q1/Q2 2023 Preliminary Design/ Consultations Procurement. Staff availability and competing priorities. Issues over standards and planning. Q3 2023 Tender/Tender Assessment of Trial Section Availability of tenderers. Price inflation. Q4 2023/Q2 2024 Construct and Monitor Trial Section Normal construction risks. Q3 2024 – Q4 2025 Report and Scale up on remainder of R161 Dependent on scheme outcomes Chief Risks In addition to possible delay factors, identify the chief risks (if any) which could hamper delivery of the initiative (3 max) 1 Planning and Environmental challenges 2 Staff availability and competing priorities
3 Negative outcomes in terms of safety and insurances Leadership Group Support Finally, please identify the nature of any required support from the Leadership Group in bringing the initiative to fruition Support the findings and recommendations of the project Assist with any ‘Roadblocks’ that may arise in terms of process and standards